Lift and Shift Project
The scope of this project is replacement of the HP3000s with next-generation HP-UX hardware and limited changes to legacy core applications and databases so they can successfully function on the modern computer hardware platforms. It is expected that this approach will provide an estimated productive functional lifespan of 10 years, providing sufficient timeframe for SBCTC to implement a long-term strategy of modernizing the core applications with a commercial Enterprise Resource Planning (ERP) solution.
Status Highlights 11/19/09
- The Schedule for Project Technical Work is at 8% complete.
- First Speedware deliverable on schedule for end of December.
- 1st QA Report published by Sterling Associates.
- All Project Hardware and Software now purchased.
- Dev/Test Environment installed and functional.
- Detail Test Planning by SBCTC-ITD continues.
- Additional Unit Test Cases being developed by SBCTC-ITD staff.
- Weekly Status Meetings held with Speedware Project Management.
- Production system being installed at DIS data center in Olympia.
- Project Technical Timeline is 18 months from September 21!